ACC Newsroom

May 2012 Update – Elgin Campus

May 2012 Update – Elgin Campus
The steel structure is almost completely erected. Soon the exterior stud framing, curtain walls, windows, and masonry will follow starting on the south facade working counter-clockwise. Meanwhile, the site paving is continuing with the bulk of the paving done already. Work is progressing nicely. The project...

Elgin Center Offers Summer Classes

See the ACC course schedule for summer classes at the Elgin Center....

April 2012 – Elgin Campus Update

April 2012 – Elgin Campus Update
We have started to go vertical! Steel erection began April 19. The building will be erected in three sections from floor to roof. It is expected to be complete by early June. One of the driveways and the south parking lot will be poured by the end of April. The north parking lot and two other driveways will...

ACC Elgin Center Hosts Registration Round Up April 25 & 26

ACC Elgin Center Hosts Registration Round Up April 25 & 26
The Austin Community College District is holding a Registration Round Up in Elgin for residents interested in taking college classes during the summer semester. The round up takes place 4-7 p.m. Wednesday, April 25, and Thursday, April 26, at the ACC Elgin Center (902 W. Second St.). College staff will be on...

March 2012 – Elgin Campus Update

March 2012 – Elgin Campus Update
The crawl space mudslab and first-floor slab have been poured. Steel erection will begin by the middle of April. Underground utilities are still in progress. The driveways and parking lots will be poured in the coming weeks. The submittal/shop drawing phase is well under way. The project team is continuing...

February 2012 – Elgin Campus Update

February 2012 – Elgin Campus Update
Installation of underground site utilities is well under way. All piers have been drilled and poured. The structural concrete has been poured for the area ways and elevator pit. The crawlspace mud slab will be poured the first week of March. Meanwhile, the submittal review process is...

January 2012: Elgin Campus Update

January 2012: Elgin Campus Update
Erosion controls are installed as well as the construction entrance and job trailer. Many truckloads of dirt have made their way to the site, and now Skanska is grading the site (including the building pad) and working on underground utilities. They expect to start drilling piers later this month. Recent...

November 2011: Elgin Campus Update

November 2011: Elgin Campus Update
The site development permit has been issued by the City of Elgin, and Skanska is mobilizing onto the site. Erosion controls are being installed, and earthwork will begin soon. The building construction documents have been completed and are currently being reviewed by the city. A building permit is...

ACC Breaks Ground on Elgin Campus

ACC Breaks Ground on Elgin Campus
Check out the slideshow of images and event video at the bottom of this page. Even a storm couldn’t stop the ACC Elgin Campus groundbreaking. The college broke ground on the new campus November 15 – indoors, with the ceremony moved from the campus site at Highway 290 and County Line Road to Elgin’s...

ACC Celebrates Groundbreaking for New Elgin Campus Nov. 15

ACC Celebrates Groundbreaking for New Elgin Campus Nov. 15
Due to possible severe weather, the ACC Elgin Campus groundbreaking event will now take place at Stardust Ballroom/Elgin S.P.J.S.T. Hall, 702 N. Hwy. 95 in Elgin. The time remains 10 a.m. to noon. Shuttles will take guests from the stadium lot at Elgin High School (14000 County Line Rd.) as originally...