ACC Puts Finishing Touches on Hays Campus; Student Registration Open

ACC Puts Finishing Touches on Hays Campus; Student Registration Open
Major construction work is complete for the new Austin Community College Hays Campus, set to open in January. It is the first community college campus in Hays County and is expected to enroll nearly 1,000 students in the spring. “Our family has watched the campus go up since the groundbreaking last year,...

October 2013 – Hays Campus Update

October 2013 – Hays Campus Update
Construction is substantially complete as of Sept. 26, 2013. We received certificates from the City of Kyle and Gensler Architects to certify completion. During the first couple weeks of October, representatives of the design and construction team and ACC met for many hours over many days to walk through...

September 2013 – Hays Campus Update

September 2013 – Hays Campus Update
We are on schedule and on budget as of this month! Construction is about 90 percent complete, and we are slowly ramping down staffing at the Hays Campus construction site. There are 140 employees representing 67 sub-contractors working on a daily basis to complete the campus in time for the spring...

July 2013 – Hays Campus Update

July 2013 – Hays Campus Update
Construction is about 75 percent complete, and we have reached peak staffing at the Hays Campus construction site. There are 165 workers representing 60 sub-contractors working on a daily basis to complete the campus in time for the spring semester. On the exterior work, all brick and limestone has been set...

June 2013 – Hays Campus Update

June 2013 – Hays Campus Update
With construction 65 percent complete, we are nearing a milestone this month. Pedernales Electric Cooperative will connect power so air conditioners can operate, allowing workers to install interior wall and floor finishes more quickly. We are nearing the peak staffing onsite daily — 140 workers...

April 2013 – Hays Campus Update

April 2013 – Hays Campus Update
Northwest Exterior of Hays Campus in April 2013. Construction is moving along well. The project is about 40 percent complete. There are more than 130 workers on-site every day, representing 12 subcontractors. The building is being “dried in.” Three subcontractors are continuing to erect exterior...

March 2013 – Hays Campus Update

March 2013 – Hays Campus Update
Construction is moving along with greater momentum now. The project is about 30 percent complete. There are now more than 100 workers on-site every day, representing 13 subcontractors. The structural steel building frame is fully erected and complete. The second- and third-floor concrete decks have been...

ACC Marks Milestone in Hays Campus Construction

ACC Marks Milestone in Hays Campus Construction
Austin Community College is celebrating a milestone in the construction of its Hays Campus. ACC and Flintco, the construction manager, marked the project’s “topping out” March 5 – signifying completion of the campus’s structural frame. “It is exciting to see this campus taking shape, thanks to...

Community Impact – ACC Hays Campus on Pace for 2014 Opening

Community Impact – ACC Hays Campus on Pace for 2014 Opening
Community Impact – ACC Hays Campus on Pace for 2014...

November 2012 – Hays Campus Update

November 2012 – Hays Campus Update
Great progress has been made in the last several weeks.  The City of Kyle issued the site development permit and building permits (one for each floor) in mid-October.  The buyout of sub-contracts is now 95 percent complete. We are happy to report that our HUB percentage for the project will exceed 30...