March Progress Report: Framing and MEP continues at ACC Highland and Rio Grande campuses

At ACC Highland Phase 2, construction teams continue work on framing, steel erection, and the exterior shell. Exterior window installation also continues, along with mechanical, electrical, and plumbing work

    

At Rio Grande Campus, crews have completed pouring walls at the north basement mechanical room and are working on electrical and telecom systems. Metal wall framing also has gone up on the second and third floors, walls are being installed in the south atrium, and crews are pouring columns in the campus ACCelerator. In the coming weeks, work will focus on window removal and duct installation.