bond projects

September Bond Projects Update

Posted on Thu, 09/12/2019 - 8:36am

Construction crews at Highland Phase 2 and Rio Grande campuses have been hard at work this summer to make progress on the sites. Highland Campus Phase 2 constructionBy: Pamela Collier, ACC Highland Phase 2 Project Manager August was another busy...

Continue reading


Construction begins at ACC Highland, Building 3000

Posted on Wed, 09/11/2019 - 12:20pm

Construction is underway at ACC Highland, Building 3000 (HLC 3000), the former women's Dillard's. The 185,000-square-foot building will be developed in phases. The first phase will serve as home to the new ACCTV studios and offices. The space will...

Continue reading


May 2019 Bond Projects Update

Posted on Tue, 05/14/2019 - 12:10pm

Highland Campus Phase 2 ACC Highland Campus Phase 2 progress continues despite the wet weather. The roofing on the north building is 95 percent complete and 65 percent complete on the south building, and exterior sheathing is 85 percent complete. In...

Continue reading


Highland and Rio Grande bond project updates: April 2019

Posted on Wed, 04/10/2019 - 12:22pm

Highland Campus Phase 2 Construction crews continue work on Highland Campus Phase 2. Structural steel erection was completed in February. Shoring and formwork for the connector bridge and social stair foundation at the paseo have started. The paseo...

Continue reading


Highland and Rio Grande bond project updates: February 2019

Posted on Thu, 02/21/2019 - 11:37am

Austin Community College (ACC) continues to move forward on phase 2 of the Highland Mall redevelopment and the renovation of Rio Grande Campus. Both projects are part of the capital improvement projects approved by district voters in the November...

Continue reading


Bond project construction updates: Highland and Rio Grande

Posted on Wed, 12/19/2018 - 2:30pm

ACC continues to make progress on $386 million in capital improvement projects approved by ACC District voters in the November 2014 bond election. In 2018, the college celebrated expanding to Leander with the opening of San Gabriel Campus and held...

Continue reading


2018 Year In Review

Posted on Tue, 12/18/2018 - 4:06pm

2018 has been an eventful year for Austin Community College. The college opened one new campus and three new buildings, launched its first bachelor degree program, established exciting new partnerships, completed its website redesign, and hosted its...

Continue reading