Rio Grande Campus

Take a look inside the future of Rio Grande Campus: Office mock-ups on display now

Posted on Thu, 10/17/2019 - 11:24am

Miniature offices have taken shape inside ACC Highland, Building 4000. The project teams for the ACC Rio Grande Campus renovations developed mock-office displays for ACC employees and staff to visit and explore the new furniture options for the main...

Continue reading


Construction updates at Highland and Rio Grande: October 2019

Posted on Mon, 10/14/2019 - 1:01pm

Rio Grande Campus RenovationsBy: Paul Mason, Rio Grande Renovation Project Manager Work on Rio Grande Campus Building 1000 is proceeding along smoothly this month. ELECTRICALElectrical panel rough-in at the main electrical room is complete. HVAC...

Continue reading


September Bond Projects Update

Posted on Thu, 09/12/2019 - 8:36am

Construction crews at Highland Phase 2 and Rio Grande campuses have been hard at work this summer to make progress on the sites. Highland Campus Phase 2 constructionBy: Pamela Collier, ACC Highland Phase 2 Project Manager August was another busy...

Continue reading


Construction updates at Highland and Rio Grande: August 2019

Posted on Fri, 08/16/2019 - 4:48pm

What's new at Highland Phase 2?By: Pamela Collier, ACC Highland Phase 2 Project Manager All aspects of construction have progressed as the building is large and in various stages of construction from one end to the other. Exterior curtainwall,...

Continue reading


Meet ACC’s new campus managers

Posted on Tue, 07/09/2019 - 12:08pm

This summer, ACC welcomed new campus managers at Riverside and Round Rock campuses. Tracie German was promoted to Round Rock campus manager on May 1. German has been with ACC for 15 years and has served the last 11 years in the Information...

Continue reading


Rio Grande Campus renovations_demolition

Rio Grande renovations continue at steady pace

Posted on Thu, 06/13/2019 - 12:48pm

Construction crews continue to make progress on the Rio Grande Campus renovations. In May, shoring — the process of temporarily supporting a building with props during alterations — was completed at the south mechanical room and the elevated slab...

Continue reading


May 2019 Bond Projects Update

Posted on Tue, 05/14/2019 - 12:10pm

Highland Campus Phase 2 ACC Highland Campus Phase 2 progress continues despite the wet weather. The roofing on the north building is 95 percent complete and 65 percent complete on the south building, and exterior sheathing is 85 percent complete. In...

Continue reading


Highland and Rio Grande bond project updates: April 2019

Posted on Wed, 04/10/2019 - 12:22pm

Highland Campus Phase 2 Construction crews continue work on Highland Campus Phase 2. Structural steel erection was completed in February. Shoring and formwork for the connector bridge and social stair foundation at the paseo have started. The paseo...

Continue reading


March Progress Report: Framing and MEP continues at ACC Highland and Rio Grande campuses

Posted on Wed, 03/13/2019 - 1:34pm

At ACC Highland Phase 2, construction teams continue work on framing, steel erection, and the exterior shell. Exterior window installation also continues, along with mechanical, electrical, and plumbing work.  12-18-2018 aerial HLC2 (1)....

Continue reading


ACC discusses the Truth, Racial Healing, and Transformation Campus Center

Posted on Thu, 03/07/2019 - 11:27am

Austin Community College (ACC) hosts panel discussions to examine new ways of supporting student success through the college's Truth, Racial Healing, and Transformation (TRHT) Campus Center. The events will be held Friday, March 8, from 11 a.m. to...

Continue reading


ACC selects site for Truth, Racial Healing & Transformation Campus Center

Posted on Thu, 02/21/2019 - 2:02pm

Austin Community College (ACC) selected a site at its Rio Grande Campus to serve as the college's Truth, Racial Healing & Transformation (TRHT) Campus Center. The multiyear initiative is designed to educate and examine the effects of racism,...

Continue reading